Jawaharlal Nehru National Solar Mission

Jawaharlal Nehru National Solar Mission (JNNSM)

Ministry of New & Renewable Energy

Establishing India as a global leader in solar energy through rapid deployment of solar technologies across utility-scale, rooftop, and off-grid applications.

Launch Date

January 2010

States & UTs Coverage

36

Duration

2010–2030

Activities

42

Indicators

24

Total Budget

₹86,000 Cr

Key Targets

500 GW RE by 2030

Installed Capacity

210 GW (2025)

Current Capacity

40 GW target

Rooftop Solar

50 GW in development

Solar Parks

Monitoring Mission Progress through Indicators

Last updated: Dec 2025

Showing 12 of 12 indicators

Installed off-grid solar capacity (GW)

OutputOn Track

NSM_IND003 ¡ Off-grid and Decentralised Solar Applications

▲
Target (2026)2 GW
Current1.56 GW
FrequencyQuarterly
UnitGW
Baseline: 0.494 (2017)78%

Share of solar in total installed power capacity (%)

OutcomeOn Track

NSM_IND009 ¡ Solar Share in National Power Mix

▲
Target (2030)25% Percentage
Current18 Percentage
FrequencyMonthly
UnitPercentage
Baseline: 1% (2015)72%

Solar RPO compliance rate (%)

OutcomeAt Risk

NSM_IND010 ¡ Renewable Purchase Obligation (RPO) Compliance

▲
Target (2030)43.33% Percentage
Current28 Percentage
FrequencyAnnual
UnitPercentage
Baseline: Variable by state (2016)65%

Solar capacity under CPSU Phase-II (MW)

OutputAt Risk

NSM_IND007 ¡ CPSU Phase-II Solar Projects

▲
Target (2026)8000 MW
Current4,200 MW
FrequencyQuarterly
UnitMW
Baseline: 0 (2020)53%

Solar PV manufacturing capacity under PLI (GW)

OutputAt Risk

NSM_IND008 ¡ Solar PV Manufacturing - PLI Scheme

▲
Target (2026)48 GW
Current22 GW
FrequencyQuarterly
UnitGW
Baseline: 0 (2021)46%

Installed grid-connected solar capacity (GW)

OutputAt Risk

NSM_IND001 ¡ Grid-connected Solar Power Development

▲
Target (2030)295 GW
Current123.13 GW
FrequencyMonthly & Quarterly
UnitGW
Baseline: 1.686 (2014)42%

Standalone solar agriculture pumps installed (Lakh)

OutputAt Risk

NSM_IND004 ¡ PM-KUSUM - Standalone Solar Agriculture Pumps

▲
Target (2026)35 Lakh Numbers
Current14.2 Lakh Numbers
FrequencyMonthly
UnitLakh Numbers
Baseline: 0 (2019)41%

CO2 emissions avoided through solar (Million Tonnes/yr)

ImpactAt Risk

NSM_IND012 ¡ Carbon Emissions Mitigation

▲
Target (2030)250 Million Tonnes CO2/year
Current95 Million Tonnes CO2/year
FrequencyAnnual
UnitMillion Tonnes CO2/year
Baseline: 5 (2015)38%

Rooftop solar capacity installed (GW)

OutputNeeds Attention

NSM_IND002 ¡ Grid-connected Solar Rooftop Programme

▲
Target (2027)40 GW
Current13.5 GW
FrequencyMonthly
UnitGW
Baseline: 0.5 (2015)34%

Grid-connected agriculture pumps solarised (Lakh)

OutputNeeds Attention

NSM_IND005 ¡ PM-KUSUM - Solarisation of Grid-connected Pumps

●
Target (2026)14 Lakh Numbers
Current4.8 Lakh Numbers
FrequencyMonthly
UnitLakh Numbers
Baseline: 0 (2019)34%

Employment generated in solar sector (Lakh jobs)

ImpactAt Risk

NSM_IND011 ¡ Green Jobs Creation in Solar Sector

▲
Target (2030)38 Lakh Numbers
Current12.5 Lakh Numbers
FrequencyAnnual
UnitLakh Numbers
Baseline: 1 (2015)33%

Decentralised ground/stilt-mounted solar capacity (GW)

OutputNeeds Attention

NSM_IND006 ¡ PM-KUSUM - Decentralised Ground-mounted Plants

▲
Target (2026)10 GW
Current3.2 GW
FrequencyMonthly
UnitGW
Baseline: 0 (2019)32%

About Solar Mission

Mission Overview

Establishing India as a global leader in solar energy through rapid deployment of solar technologies across utility-scale, rooftop, and off-grid applications.

Vision

To establish India as a global leader in solar energy by creating the policy conditions for solar technology diffusion across the country as quickly as possible.

Key Highlights

Installed Capacity

500 GW RE by 2030

Current Capacity

210 GW (2025)

Rooftop Solar

40 GW target

Solar Parks

50 GW in development

Key Objectives

  • Deploy 100 GW grid-connected solar power by 2022 (revised to 500 GW RE by 2030)
  • Reduce cost of solar power generation through long-term policy, large-scale deployment and R&D
  • Achieve grid-parity of solar power with conventional power by 2030
  • Create favourable conditions for solar manufacturing in India

Milestones & Achievements

✓

Achieved 123.13 GW grid-connected solar capacity (Aug 2025) — exceeding original 100 GW target

✓

Original target 20,000 MW revised to 100,000 MW (Jun 2015) — then achieved ahead of schedule

✓

PM-KUSUM deployed 14 lakh standalone solar pumps de-dieselizing farm sector

✓

48,337 MW integrated solar PV module manufacturing capacity under PLI

✓

17 lakh direct jobs created under PM Suryaghar scheme; 38 lakh total RE jobs